Andrew Stevenson, County Councillor, has received an update from Govia Thameslink about their works at Stevenage to increase rail capacity. The additional fifth platform at Stevenage is in response to increased demand for train services to and from London.
Bus replacements between Watton-at-Stone and Stevenage are due to begin on Monday 20th May 2019 and last until Summer 2020. The buses will operate on weekdays and should be timed to allow connections to onward rail journeys. Weekend journeys, and those to and from London should not be impacted by the changes.
More information can be viewed below from Govia Thameslink.
I wanted to provide an update on Great Northern’s plans for passengers during the Stevenage Turnback project, including news that we expect to resume weekday rail services in the Summer 2020 timetable and that ticket acceptance has been arranged in addition to the planned bus services.
As a reminder, the Stevenage Turnback project includes the construction by Network Rail of around 2 kilometers of new, electrified railway, changes to the signalling systems, major civil engineering, and physical work at Stevenage Station including the introduction of a new fifth platform. This significant project will enable Great Northern to increase the frequency of trains to two per hour all day in each direction between Stevenage and Watton-at-Stone and will help to improve the reliability of all services.
While these works are underway, from Monday the 20th of May 2019 on weekdays, Great Northern will provide a direct bus service between Stevenage and Watton-at-Stone, and, to provide faster long-distance journeys, a second direct bus service between Stevenage and Hertford North. Watton-at-Stone will continue to be served by trains to/from London and a normal train service between Stevenage and Watton-at-Stone will continue to operate at weekends. Stevenage will continue to be served by train services operating on the East Coast Main Line as usual.
With regards to the project, I am pleased to confirm that Network Rail will complete the new infrastructure in 2020 and as a result, Great Northern expects to resume weekday train services in the Summer 2020 timetable.
I am also pleased to let you know that in addition to the dedicated bus services, we will also have ticket acceptance in place for passengers that may prefer to travel entirely by rail. This ticket acceptance will mean that passengers can travel by changing trains at Alexandra Palace or Finsbury Park at no extra cost and travel on train services operating on the East Coast Main Line to Stevenage. We expect this to be especially popular for longer distance journeys, or for passengers starting or ending their journeys at destinations towards the south of the Hertford Loop such as Bowes Park.
We continue to publicise the works and our planned alternative travel arrangements to passengers. This week as an example, we have arranged for additional staff to be on board trains all week between Stevenage and Hertford North to distribute leaflets and a small treat to passengers that are using the current service. Our ambition is to ensure wherever possible that everyone who will be impacted by the works is aware ahead of time and able to better plan their journeys.
As before, passenger and project information including details on ticket acceptance is available on the dedicated web page: https://www.greatnorthernrail.com/svgbus.