Tarmac Waterford Update May 2017

13th May 2017 6:10 pm / molewood

Below is an update from Tarmac about their work at Waterford since December.

Project Team
CRH Tarmac has appointed Ignacio Escobar – a highly qualified and experienced engineer – as the new in-house Waterford team leader. CRH Farrans Construction will now be the lead building contractor and Flanaghan and Lawrence are the architects. The project will be managed by Faithful and Gould – who will be the main contact/liaison point with the local community and myself.

Timescales
These have not yet been finalised – but we anticipate being able to share them with you over the next few weeks. Our ultimate objective is to have discharged all the planning conditions by the end of this year and to have completed the development by the end of 2018.

Discharging conditions
You may recollect that the planning permission – granted by East Herts District Council in December 2015 – was issued subject to us discharging several conditions. Some of these have to be completed prior to commencement, some prior to building/construction and some prior to occupation.

Prior to commencement Prior to building/construction Prior to occupation
1 Landscaping
Full details of hard and soft landscaping
1 Archaeology
7 trial trenches. TBC following outcome of ongoing discussions with County Archaeologist
1 Contaminated Lane
Completion and effectiveness report
2 Contaminated land
Identification and methodology for removal of any contaminated land
2 External materials
Samples to be supplied
2 Sustainability
Sustainability certificate to be issued post construction
3 Ecology
Updated bat and reptile surveys
3 Highways
Details of junction improvements for Sacombe Rd/Vicarage Lane and maintenance access to Vicarage Lane
3 Ecology
Bird box details
4 Footpath
Approval of details
4 Wheel washing
Facilities to be operated throughout construction period
4 Certificate of completion
Ref footway works
5 Footpath Route
To be walked and check for any significant habitats
5 Construction vehicles
Details of movements and access arrangements
6 Hydrology
Detailed surface water drainage scheme
7 Foul Drainage
Detailed scheme
8 Sustainability
Confirmation of Proposed Code Level 6 (or current equivalent standard)

Some of you may have noticed an unusual number of people on the site recently? You will see more of them over the next few weeks and months, as they carry out the site investigations which will allow us to discharge the conditions. Without completing the investigations and surveys identified in the attached table, we can’t discharge the planning conditions and wouldn’t be able to deliver the approved scheme.

Stakeholder Engagement
As you can probably tell just from these bare outlines, we have quite a lot of work to do in the very near future. This includes finalising our timelines, briefing the consultants – and then evaluating their reports. As ever, keeping in touch with you all remains one of our key objectives – which is why we thought we would give you the good news as soon as we could.

However, we will have to ask you to be patient with us for just a little longer, while we dot the i’s and cross the t’s.

Footpath
Many thanks to those of you who gave us your feedback on the new footpath. These have all been forwarded to County Highways – and we await their response.

Posted in: News

Comments are closed.

Post Navigation

← Previous Post
Next Post →

Upcoming Events

Notice
There are no upcoming events.

Recent Posts

  • Bengeo Community Event
  • Sacombe Rd to be partially closed
  • Bengeo Mosaic revealed
  • Bengeo Community Garden Bingo
  • Spring 2026

Links

  • Local Links
  • Neighbourhood Watch
  • Newsletters
  • Travel Info
  • Olde Molewood
  • In The Area
  • Go Hertford
  • Subscriptions
© Copyright 2026 - Molewood Residents Association
Infinity Theme by DesignCoral / WordPress